Planche v Colburn (1831) 8 Bing 14; 131 ER 305
Planche v Colburn shows that where one party's breach prevents the other from completing performance, the innocent party may claim a reasonable sum for work done, rather than being defeated by the entire obligations rule.
Facts
The defendants were publishers producing a series of books called The Juvenile Library. They engaged the claimant to write a volume for the series on the subject of costume and ancient armour, for a fee of one hundred pounds payable on completion. The claimant began work: he carried out research and wrote part of the book. Before he had finished, the defendants abandoned the series. The claimant had not delivered a completed manuscript and was not paid. He sued for payment for the work he had done, relying on the publishers' decision to abandon the series as the reason he had been unable to finish.
Legal Issue
Could the author recover anything for his work, when the contract provided for payment only on completion and the publishers' abandonment of the series had prevented him from finishing?
Held
The Court of Common Pleas held that the claimant was entitled to recover a reasonable sum, and the jury's award of fifty pounds was upheld. Tindal CJ explained that the defendants, by abandoning the series, had put an end to the contract and prevented the claimant from performing in full. The claimant was not obliged to complete the volume and tender it for a series that no longer existed. Having been prevented from earning the agreed fee, he could treat the contract as at an end and recover on a quantum meruit for the work he had actually done. The entire nature of the payment obligation did not defeat his claim, because it was the defendants' own breach that had stopped performance.
⭐ Legal Principle
Where one party wrongfully prevents the other from completing performance, the innocent party may treat the contract as ended and recover a reasonable sum, on a quantum meruit, for the work done, as an alternative to damages for breach. The rule that payment depends on completion does not protect a party whose own breach caused the non-completion.
Significance
The case is the standard example of the prevention exception to Cutter v Powell. It is also cited as an early example of restitutionary recovery for work done under a contract terminated for breach. Modern analysis asks whether a claimant may choose between expectation damages and a quantum meruit; the point is debated in academic writing. Quantum meruit claims for work done where no contract materialises, as in British Steel v Cleveland Bridge, rest on a related but distinct basis.
Common exam questions about this case
Why could the author recover in Planche v Colburn despite not completing the book?
The publishers abandoned the series, which prevented the author from completing and delivering the volume. Because their breach stopped performance, the author was not bound by the requirement to complete before payment. He could treat the contract as ended and recover a reasonable sum for the work done, and the jury's award of fifty pounds was upheld.
How does Planche v Colburn relate to Cutter v Powell?
Cutter v Powell holds that a party who fails to complete an entire obligation cannot recover. Planche v Colburn is an exception: where non-completion is caused by the other party's wrongful prevention, the performing party may recover a reasonable sum for what has been done. The difference lies in who is responsible for the failure to complete.
What is a quantum meruit?
A quantum meruit is a claim for a reasonable sum for work done or services supplied. It may arise where a contract has been terminated by the other party's breach, as in Planche v Colburn, where work is done under a contract that never comes into existence, as in British Steel v Cleveland Bridge, or where a contract does not fix the price.