Metropolitan Water Board v Dick, Kerr & Co Ltd [1918] AC 119

Copy OSCOLA citation
Writing an essay? Build your full OSCOLA reference list →
Topics:Frustration

Metropolitan Water Board v Dick, Kerr shows that a long government-ordered interruption can frustrate a construction contract, and that a delay clause will exclude frustration only if it was intended to cover the event that actually occurred.

Facts

In 1914 the contractors agreed to build a reservoir for the Water Board within six years. The contract contained a clause allowing the engineer to grant an extension of time if the works were delayed by any cause, including difficulties or impediments of any kind. In 1916, during the First World War, the Minister of Munitions, acting under wartime powers, ordered the contractors to stop work and to sell much of their plant. The contractors argued that the contract had been frustrated. The Board argued that the extension of time clause covered the delay, so the contract remained in force and would resume after the war.

Legal Issue

Was the contract frustrated by the government's order to stop work, or did the extension of time clause provide for the interruption so that the contract continued?

Held

The House of Lords held that the contract was frustrated. The interruption was of such a character and duration that, if the contract were resumed after the war, it would in effect be a different contract from the one the parties had made. Economic conditions, prices and the availability of labour and materials would be fundamentally altered. The extension of time clause did not prevent frustration. On its proper construction, it was intended to deal with temporary difficulties and ordinary delays in the course of the work, not with a prolonged interruption of indefinite length caused by legislative intervention in wartime, which destroyed the basis of the contract.

⭐ Legal Principle

A contract is frustrated where an interruption, such as one caused by government intervention, is of such a character and duration that resumed performance would be fundamentally different from what was agreed. A clause dealing with delay will exclude frustration only if, properly construed, it covers the actual event and its full extent.

Significance

The case is a leading example of frustration by delay and government intervention, alongside Jackson v Union Marine Insurance. It also establishes the important point that express provision for an event excludes frustration only if the clause truly covers what happened, a point later applied to force majeure and other risk allocation clauses. The modern radical difference test was later articulated in Davis Contractors v Fareham UDC, where mere delay and expense were not enough.

Common exam questions about this case

Why was the contract frustrated in Metropolitan Water Board v Dick, Kerr?

The government ordered the contractors to stop work and sell their plant during the war. The House of Lords held that the interruption was so long and of such a character that resuming the contract after the war would amount to performing a fundamentally different contract, given the changed economic conditions. The contract was therefore discharged.

Why did the extension of time clause not prevent frustration?

A clause will exclude frustration only if it was intended to cover the event that occurred. The extension of time clause was construed as dealing with ordinary, temporary delays in the progress of the works, not a prolonged, government-ordered stoppage of indefinite length. Because the event fell outside the clause, the doctrine of frustration could still operate.

How does Metropolitan Water Board v Dick, Kerr compare with Davis Contractors v Fareham UDC?

In Dick, Kerr, a long wartime stoppage by government order made resumed performance fundamentally different, so the contract was frustrated. In Davis Contractors, labour shortages caused delay and additional cost, but the work remained the same in nature, so there was no frustration. The contrast shows that the question is whether performance would be radically different, not merely more difficult or expensive.