British Westinghouse Electric and Manufacturing Co Ltd v Underground Electric Railways Co of London Ltd [1912] AC 673; (1912) 50 SLR 617
British Westinghouse is the foundation of the mitigation rules. A claimant cannot recover loss it could reasonably have avoided, and where the steps it actually takes reduce the loss, the benefit is set against the damages.
Facts
Under a contract made in March 1902 with the Metropolitan District Electric Traction Company, on the railway side of the transaction, Westinghouse agreed to supply and erect eight steam turbines with alternators for about £250,000 to power the London lines. The turbines delivered fell short of the specification in power and in economy of working. The railway company used them for some years while reserving its claim for damages, and then replaced them with new Parsons turbines, which were so much more efficient that the savings more than covered their price. In the arbitration over damages, the arbitrator found that buying the new machines was a reasonable and prudent way of mitigating the loss, and that even if the original turbines had met the specification it would still have paid the railway company to replace them with the Parsons machines at its own expense. He stated a special case asking whether the cost of the replacements was recoverable. The High Court said it was, and the arbitrator made his award on that basis. Westinghouse's motion to set the award aside for error of law on its face was refused, and the Court of Appeal upheld that refusal.
Legal Issue
When assessing damages for breach, must the financial benefit the claimant gained by replacing the defective machines be taken into account, even though it was not obliged to replace them?
Held
The House of Lords (Viscount Haldane LC, Lord Ashbourne, Lord Macnaghten and Lord Atkinson) allowed Westinghouse's appeal and reversed the Court of Appeal. It held, first, that the court could set aside an award that was expressly based on a wrong opinion of law given on a special case. Secondly, the financial advantage the railway company gained from the superior Parsons turbines was relevant to the assessment of damages, and the award was sent back to the arbitrator with a declaration to that effect. Viscount Haldane LC explained that damages aim to compensate for the pecuniary loss flowing naturally from the breach, but this is qualified by the rule that the claimant must take all reasonable steps to mitigate and cannot claim loss caused by failing to do so. The claimant is not bound to take steps that a reasonable and prudent person would not take in the ordinary course of business. However, where it does take steps arising out of the breach that in fact reduce its loss, the resulting benefit must be set against the loss, whether or not those steps were required. Because the savings from the new machines exceeded their cost, the cost of the replacements could not be claimed.
⭐ Legal Principle
A claimant cannot recover damages for loss that it could have avoided by taking reasonable steps after the breach. Where the claimant does take reasonable steps that arise out of the breach and reduce its loss, the benefit obtained is deducted from the damages, even if the claimant was not obliged to take those steps.
Significance
The case states both limbs of mitigation: the avoidable loss rule and the duty to give credit for benefits. Strictly, mitigation is not a duty owed to the defendant; failure simply bars recovery of the avoidable loss, and reasonable costs incurred in mitigating are recoverable. The Supreme Court in Globalia v Fulton Shipping (The New Flamenco) clarified that only benefits legally caused by the breach are deducted, not those from independent transactions such as a later sale in a falling market. Mitigation does not usually apply to a debt claim for the price, as White and Carter v McGregor shows.
Common exam questions about this case
What two principles did British Westinghouse establish?
First, a claimant cannot recover for loss it could have avoided by taking reasonable steps after the breach. Second, where the claimant does take steps arising out of the breach that reduce its loss, the benefit must be set off against the damages, even if those steps went beyond what mitigation required. Both limbs come from Viscount Haldane LC's speech.
Is there a duty to mitigate?
Not in the sense of an obligation owed to the defendant. British Westinghouse uses the language of duty, but the effect is that the claimant simply cannot recover the part of its loss that reasonable steps would have avoided. The standard of reasonableness is not demanding, the burden of proving failure lies on the defendant, and reasonable costs of mitigating can be claimed.
Which benefits must be deducted after British Westinghouse?
Only benefits legally caused by the breach. In Globalia v Fulton Shipping (The New Flamenco) the Supreme Court held that an owner who sold a ship after early redelivery did not have to credit the saving from selling before prices fell, because the sale was an independent decision, not caused by the breach. The replacement turbines in British Westinghouse arose directly from the breach, so their savings counted.